Construction updates and project timeline
Temporary construction impacts
I-205
Nighttime northbound off-ramp closure to OR 99E (exit 9) on the following dates:
Friday, Mar. 13 from 10 p.m. to 5 a.m.
Thursday, Mar. 19 and Friday, Mar. 20 from 10 p.m. to 5 a.m. both night
Nighttime southbound lane closures on the following dates:
Friday, Mar. 13 from 10 p.m. to 5 a.m. each night.
Monday, Mar. 16 to Friday, Mar. 20 from 10 p.m. to 5 a.m. each night.
Nighttime southbound off-ramp closure to OR 43 (exit 8) on the following dates:
Wednesday, Mar. 18 and Thursday, Mar. 19 from 10 p.m. to 5 a.m. both nights.
OR 99E
Nighttime lane closures on the following dates (one lane will remain open in each direction):
Friday, Mar. 13 from 8 p.m. to 6 a.m.
Monday, Mar. 16 to Friday, Mar. 20 from 8 p.m. to 6 a.m. each night.
Nighttime northbound on-ramp closure to I-205 Thursday, Mar. 19 and Friday, Mar. 20 from 10 p.m. to 5 a.m. both nights
Pedestrian detours
OR 43
Nighttime northbound lane closures Monday, Mar. 16 to Monday, Mar. 23 from 8 p.m. to 6 a.m. each night
Nighttime southbound lane closures Friday, Mar. 13 from 8 p.m. to 6 a.m. each night
Pedestrian detours
Clackamette Drive
Daytime flagging on Clackamette Drive on the following dates:
Friday, Mar. 13 from 7 a.m. to 5:30 p.m.
Monday, Mar. 16 to Thursday, Mar. 19 from 7 a.m. to 5:30 p.m. each day.
Main Street
Daytime flagging on Main Street on the following dates:
Friday, Mar. 13 and Saturday, Mar. 14 from 7 a.m. to 5:30 p.m. both days.
Monday, Mar. 16 to Saturday, Mar. 21 from 7 a.m. to 5:30 p.m. each day.
Updated: Mar. 13, 2026
Regional construction impacts
Construction noise in West Linn
Over the next couple of months, there is demolition work planned in West Linn on the north and south side of I-205. Crews are working to remove the concrete deck of the former elevated on-ramp from OR 43 to I-205 north. This ramp was replaced with the new roundabout that opened in 2023. The work is planned for approximately two weeks and will happen during nighttime hours.
In mid-March after the concrete removal is complete, crews start the removal of the elevated on-ramp itself along with the columns below the I-205 southbound off-ramp to OR 43. This will take approximately 3-4 weeks and most of the work will happen during the day, but some of the work may continue into the evening.
Nearby residents and businesses may hear noise from this demolition work. Use the 24/7 noise hotline to report any noise concerns: 503-276-7809.
As with any construction project, closure dates and timing are subject to change due to weather or other unforeseen events. Please continue to check back for ongoing updates.
Ongoing construction impacts
Traffic
OR 43 northbound single lane closure with trucks leaving and entering the highway.
Clackamette Drive single lane closure with temporary signal and flagger.
Jon Storm Park parking lot under the Abernethy Bridge closed during construction.
Local roads will experience lane closures and traffic restrictions during construction.
Noise
People who live and work in the project area will hear noise from construction equipment and vehicles, pile driving, bridge demolition, and other construction-related noise sources.
24/7 Noise Hotline: 503-276-7809. This number is available for nearby residents and businesses to help resolve any ODOT noise-related concerns 24 hours a day.
For more information see project noise study »
Light
Stationary lights with low lumens will be placed in the river to alert boaters.
River
The Willamette River remains accessible during Abernethy Bridge construction; the Sportcraft Boat Ramp is open.
'No wake' zones are in place during 2024 through the bridge construction area on the Willamette River.
River users will notice several large barges anchored in the river and are required to stay 200 feet away from them. River users are urged to use extreme caution, and all boats must travel between the green and red buoys.
Bike and Pedestrian
Bike and pedestrian routes through construction zones are in place. People walking and riding a bike need to use caution when traveling through the project area. Follow signs and stay alert.
OR 43 and OR 99E bike and pedestrian access restrictions.
Transit
No impacts.
Watch to learn about recent project developments.
Video of television interview with project leaders.
Project timeline
Construction began in the summer of 2022 and is expected to conclude in 2026.